Writing Execution Plan for sustainable house

Description

The project aimed to construct a sustainable, energy-efficient house encompassing three bedrooms, a living room, a dining room, an indoor and outdoor kitchen, along with a garden swimming pool. The objectives were to minimize environmental impact, incorporate renewable energy sources, efficient water management systems, and environmentally friendly materials. The project’s completion was targeted within one year, adhering to a maximum budget of $ 200,000.

Don't use plagiarized sources. Get Your Custom Assignment on
Writing Execution Plan for sustainable house
From as Little as $13/Page

Project Scope and Objectives:

Land area: 350 square meters
Maximum budget: $ 200,000
Project duration: One year
Sustainable elements:

Execution Plan Outline:

Fiberglass Rebars Implementation: (Supplier IKK MateenBar) https://ikkmateenbar.com/
Making sure the delivered FG rebars match the approved sample and size
Installing the rebars as per the structure drawing of the building.
Ensure the quality of installation before pouring concrete
Give the green light to the project manager to arrange concrete pouring implementation.
Thermal Insulation System (EIFS): (Supplier: PLEKO) https://pleko.com/_main/
Train the installers team on mock up sample for EIFS to optimize energy efficiency and improve insulation.
Supervised installation to maintain quality standards and provide an airtight building envelope.
Partnered with water management experts to design and install a gray water system for efficient water recycling and reduced water consumption.
Conducted tests to ensure functionality and compliance with environmental standards.
Gray Water System Integration: (Contractor: IWS Bahrain) https://www.iws.bh/products/water-solutions/grey-w…
Thermally Insulated Glass Installation: (Supplier: Alyusuf for thermo glass)
Sourced high-quality thermally insulated glass for the sunroof to maximize natural light while minimizing heat transfer.
Oversaw installation procedures to guarantee proper sealing and energy efficiency.
Collaborated with solar energy specialists to select and install panels suitable for the house’s energy needs.
Conducted feasibility studies and inspections to optimize panel placement and maximize energy generation.

Solar Energy Panels Setup: (Supplier: Tamimi Energy)

Green Landscape Design: Supplier: NASS Landscape)
Implemented eco-friendly practices for irrigation and plant selection to conserve grey water and support biodiversity.

Challenges and Mitigation:

Cost management: Regular budget monitoring and efficient resource allocation ensured adherence to the BD 200,000 budget.
Timely completion: Continuous monitoring of construction progress and proactive problem-solving minimized delays.

Managing the Team

Identifies labor strengths and assign roles based on their natural abilities.
Motivate team to contribute to high performance.
Free lunch for the team who finish their task before the deadline and meet quality needs.
Ensures a well-balanced team with diverse skills

Conclusion:

The successful execution of the sustainable, energy-efficient house project was achieved through meticulous planning, effective collaboration with experts, and a commitment to environmental consciousness. The house stands as a testament to modern living that minimizes environmental impact while offering comfort and functionality.

Recommendations:

Regular maintenance and monitoring of installed systems to ensure long-term efficiency.
Documentation and sharing of best practices with stakeholders for future sustainable projects.