Finance Question

Description

Hello everyone

Don't use plagiarized sources. Get Your Custom Assignment on
Finance Question
From as Little as $13/Page

I kindly need your help with the below assignemnt please:

Cash Flows and Capital Budgeting Techniques

Complete the following problems:

Problem 1: Net Present Value (NPV) and Internal Rate of Return
Problem 2: Profitability Index (PI) and Payback Period
Problem 3: Uneven Cash Flows
Problem 4: Calculating Free Cash Flows
Problem 5: Calculating project cash flows and NPV

Following the data provided on the attached PDF complete the problems in an Excel spreadsheet. Be sure to show all your work on the Excel spreadsheet to receive credit; no hard keys.

Find the attached files please, Thanks.

Regards
Abdul


Unformatted Attachment Preview

Name
QT Rubric_5q_100
Description
100 points
Rubric Detail
Levels of Achievement
Criteria
Exceeds Expectation
Meets Expectation
Some Expectations
Unsatifactory
Problem
1
19 to 20 points
17 to 18 points
15 to 16 points
0 to 14 points
All components are correct,
with no errors or omissions. All
work is shown.
Some significant but not
major errors exist. Some
work is shown.
Some major errors or
omissions exist. Limited
work is shown.
Fails to demonstrate
adequate comprehension
of the concept.
Problem
2
19 to 20 points
17 to 18 points
15 to 16 points
0 to 14 points
All components are correct,
with no errors or omissions. All
work is shown.
Some significant but not
major errors exist. Some
work is shown.
Some major errors or
omissions exist. Limited
work is shown.
Fails to demonstrate
adequate comprehension
of the concept.
Problem
3
19 to 20 points
17 to 18 points
15 to 16 points
0 to 14 points
All components are correct,
with no errors or omissions. All
work is shown.
Some significant but not
major errors exist. Some
work is shown.
Some major errors or
omissions exist. Limited
work is shown.
Fails to demonstrate
adequate comprehension
of the concept.
Problem
4
19 to 20 points
17 to 18 points
15 to 16 points
0 to 14 points
All components are correct,
with no errors or omissions. All
work is shown.
Some significant but not
major errors exist. Some
work is shown.
Some major errors or
omissions exist. Limited
work is shown.
Fails to demonstrate
adequate comprehension
of the concept.
Problem
5
19 to 20 points
17 to 18 points
15 to 16 points
0 to 14 points
All components are correct,
with no errors or omissions. All
work is shown.
Some significant but not
major errors exist. Some
work is shown.
Some major errors or
omissions exist. Limited
work is shown.
Fails to demonstrate
adequate comprehension
of the concept.
View Associated Items
Print
Close Window
Problem 1: Net Present Value (NPV) and Internal Rate of Return
You are considering a project with an initial cash outlay of 50,000 SAR and expected free cash flows of 15,000 SAR at the end
a. What is the projects’s NPV?
b. What is the project’s IRR?
c. Is the project acceptable based on NPV and IRR decision criteria.
Problem 2: Profitability Index (PI) and Payback Period
You are considering a project with an initial cash outlay of 66,000 SAR and expected free cash flows of 23,000 SAR at the end
a. What is the project’s payback period?
b. What is the project’s profitabiity Index?
Problem 3: Uneven cash flows
A firm is considering the two following projects with amounts in SAR.
(a) Calculate the NPV for each project assuming a discount rate of 5%.
(b) Explain which project is better and why.
Data
Project A
Rate
Cash outflow:
Cash Inflows:
5%
-23,000,000
3,500,000
7,500,000
10,000,000
12,000,000
Project B
5%
-63,000,000
19,000,000
15,000,000
9,000,000
8,000,000
Problem 4: Calculating the free cash flows
A firm is considering a new project with a 4-year life with the following cost and revenue data. This project with require an inv
This new equipment will be depreciated down to zero over 4 years using the simplified straight-line method and has no salva
This new project will generate additional sales revenues of 100,000 SAR whereas additional operating costs, excluding deprec
The company’s marginal tax rate is 35 percent. What is the project free cash flow in year 1?
Problem 5 Calculating project cash flows and NPV
A corporation is considering the purchase of new equipment. Although the machine being considered will result in an increas
This machine has an expected life of 8 years, after which it will have no salvage value. Also, assume that there is simplified st
a. What is the initial outlay assoicated with this project?
b. What are the annual after-tax cash flows associated with thisproject for years 1 through 9?
c. What is the terninal cash flow in year 10?
nsidered will result in an increase in earnings before interest and taxes of 25,000 SAR per year, it has a purchase price of 108,000 SAR, and
rchase price of 108,000 SAR, and it would cost an additional 3,000 SAR to properly install the machine.

Purchase answer to see full
attachment